What happened at last night’s meetings
Here are my notes from last night:
Vehicle purchases – Council approved the purchase of a dozen vehicles, everything from an ambulance to an excavator. Generally, we will approve all of these vehicles all at once in a given year. The administration does its best to shop locally, and one vehicle is in fact purchased from Marhofer Chevrolet. But mostly, we need to go outside the city borders to find the best prices. When I first joined council, I was surprised by how many new vehicles were needed, but then I started looking at the maintenance costs for vehicles with over 120K miles. It’s cheaper to replace vehicles than constantly sink thousands of dollars into them. I was satisfied that each of these 2017 purchases made economic sense. Each passed council unanimously, by a 7-0 vote.
2017 road repair program – Our service director provided a spreadsheet of roads that the city intends to repave in 2017. You can see that list at the bottom of this post. The entire list probably will not be completed, because it includes $1.9MM of jobs, and the program is only funded for $1.5MM in 2017. It will depend on how the bids come in. (You may have noticed a Facebook live video from this portion of the meeting. I apologize that it was low quality. It’s hard to shoot video during the meeting without being a distraction.)
Primary elections – We again discussed my proposal to move primary elections from September to May, and Matt Riehl’s proposal to eliminate them altogether. Brian D’Antonio and I agreed that we could place both measures on the ballot. The mayor thought it would be too confusing. The mayor and John Pribonic preferred that we spend more time deliberating the topic. Given that we have had this on the agenda since December, I was ready to vote. My proposal failed by a 5-2 vote (Rasor, D’Antonio). Based on last night’s discussions, it appears that council will give voters the opportunity to eliminate primary elections. But it will not give the voters the opportunity to move the primary date. If that proposal fails in November 2017, then I will be ready to re-introduce my legislation to be decided by voters in November 2018. The good news is, we have plenty of time before the 2019 election, which is the first election that could be affected by our potential changes.
EMS fees – By a 7-0 vote, Council approved legislation to bring our EMS fees up to a market level, effective May 1. It will include an automatic 2% increase each year, to keep pace with the increased costs of labor, equipment, and supplies. Again, no resident will ever pay this fee. It’s all about getting our fair share from insurance companies. The increase helps ensure our paramedic teams are properly funded.
Next meeting – Council will meet next on April 27.
| 2017 PROPOSED ROAD PROGRAM – ESTIMATE ONLY | ||||||
| 2017 PROPOSED ASPHALT RESURFACING PROGRAM | ||||||
| ROUTE | ID | DESCRIPTION | LENGTH | WIDTH | AREA SQYD | CAPITAL FUND |
| Marsh Road | MA-25-3284 | Kent to N River | 3880.00 | 22.00 | 9484.44 | $105,656.66 |
| Clarke Drive | CL-11-4901 | Pebblehurst to Cul-de-sac | 512.00 | 22.00 | 1251.56 | $16,608.20 |
| Pebblehurst Drive | PE-11-4996 | W/Clarke to Cul-de-sac | 525.00 | 22.00 | 1283.33 | $17,029.79 |
| Pebblehurst Drive | PE-11-4830 | Call to Temp End | 1624.00 | 23.00 | 4150.22 | $55,073.42 |
| Peterboro Drive | PE-13-3074 | Concrete to Berry to 187′ E | 334.00 | 22.00 | 816.44 | $10,834.16 |
| Knob Hill | KN-13-4512 | Berwin to Cul-de-sac | 454.00 | 22.00 | 1109.78 | $14,726.78 |
| Daisy Hill | DA-13-4506 | Berwin Drive to Cul-de-sac | 311.00 | 22.00 | 760.22 | $10,088.12 |
| Berry Hill | BE-13-4553 | Peterboro to Cul-de-sac | 981.00 | 22.00 | 2398.00 | $31,821.46 |
| Berwin Drive | BE-13-3107 | Berry Hill to 660′ E | 660.00 | 22.00 | 1613.33 | $21,408.89 |
| Berwin Drive | BE-13-3140 | 660′ E Berry Hill to Phase Line | 847.00 | 22.00 | 2070.44 | $27,474.74 |
| Hawthorne Avenue | HA-22-1920 | Darrow to Margaret | 880.00 | 20.00 | 1955.56 | $21,784.94 |
| Margaret Avenue | MA-22-3349 | End to End | 970.00 | 20.00 | 2155.56 | $24,012.94 |
| Thorndale Avenue | TH-22-1934 | Yukon to Margaret | 738.00 | 20.00 | 1640.00 | $18,269.60 |
| Beech Street | BE-21-1837 | Elm to W/Library 2nd Drive | 280.00 | 18.00 | 560.00 | $6,238.40 |
| Elm Road | EL-21-3764 | Marc’s Driveway to Graham | 200.00 | 20.00 | 444.44 | $4,951.06 |
| Elm Road | EL-21-3541 | Kent to Marc’s Driveway | 2550.00 | 20.00 | 5666.67 | $75,196.71 |
| Maplewood Road | MA-15-1929 | Darrow to Stow | 2940.00 | 18.50 | 6043.33 | $67,322.70 |
| Hibbard Drive | HI-09-1249 | Hudson to 125′ E | 125.00 | 37.00 | 513.89 | $6,819.32 |
| Hibbard Drive | HI-09-1271 | Algonquin to 150′ W/ Sunnyside | 1657.00 | 31.00 | 5707.44 | $75,737.73 |
| Hibbard Drive | HI-09-1442 | Darrow to 150′ W/Sunnyside | 2975.00 | 23.00 | 7602.78 | $84,694.97 |
| Hibbard Drive | HI-09-1257 | 125′ E/Hudson to Algonquin | 366.00 | 37.00 | 1504.67 | $19,966.97 |
| Markwood Drive | MA-09-4680 | Hibbard to End | 960.00 | 22.00 | 2346.67 | $26,141.90 |
| Eagle Avenue | EA-08-4343 | Housley to Temp End | 850.00 | 23.00 | 2172.22 | $28,825.36 |
| Housley Road | HO-08-1300 | Plover to 410′ E of Ellsworth | 842.00 | 22.00 | 2058.22 | $27,312.58 |
| Mallard Avenue | MA-08-4343 | Housley to Temp End | 850.00 | 23.00 | 2172.22 | $28,825.36 |
| Steels Corners Road | ST-35-0002 | end concrete to begin concrete | 107.82 | 32.00 | 383.36 | $5,087.19 |
| Steels Corners Road | ST-35-0004 | end concrete to begin concrete | 82.94 | 32.00 | 294.90 | $3,913.32 |
| Wyndham Ridge Drive | WY-18-4050 | Steeles to 3950 | 500.00 | 22.00 | 1222.22 | $16,218.86 |
| Kings Mill Boulevard | KI-24-4036 | Graham to Crownpoint | 421.02 | 28.00 | 1309.84 | $17,381.58 |
| Crown Pointe Drive | CR-24-3175 | E/Bishops to E/Queensbury | 435.00 | 22.00 | 1063.33 | $14,110.39 |
| Crown Pointe Drive | CR-24-3209 | E/Queensbury to S/Courtwood | 520.00 | 22.00 | 1271.11 | $16,867.63 |
| Courtwood Way | CO-24-3190 | Crown Pointe to Cul-de-sac | 210.00 | 22.00 | 513.33 | $6,811.89 |
| Queensbury Circle | QU-24-4008 | Crown Ponte to Cul-de-sac | 475.00 | 22.00 | 1161.11 | $15,407.93 |
| Darrow Road | DA-35-3451 | just south of Kent Road to just north | 442.79 | 48.00 | 2361.55 | $31,337.77 |
| Kent Road | KE-35-3352 | begin 5 lanes to end 5 lanes | 650.00 | 56.00 | 4044.44 | $53,669.72 |
| $1,007,629.03 | ||||||
| 2017 PROPOSED CONCRETE OVERLAY PROGRAM | ||||||
| ROUTE | ID | DESCRIPTION | LENGTH | WIDTH | AREA SQYD | CAPITAL FUND |
| Saybrooke Boulevard | SA-13-2929 | Wexford to Bike Trail | 1605.00 | 22.00 | 3923.33 | $60,497.80 |
| Hampton Circle | HA-13-0000 | Saybrooke to Cul-de-sac | 334.00 | 22.00 | 816.44 | $12,589.57 |
| $73,087.37 | ||||||
| 2017 PROPOSED ASPHALT RESURFACING PROGRAM – OTHER INFRASTRUCTURE | ||||||
| ROUTE | ID | DESCRIPTION | LENGTH | WIDTH | AREA SQYD | CAPITAL FUND |
| Silver Springs Park Stow Road entrance | Full depth repair and resurface | 400.00 | 21.00 | 933.33 | ||
| Silver Springs Park Bow Wow Beach | Full depth pavement install | 260.00 | 20.00 | 577.78 | ||
| City Hall Parking Lot | Mill and resurface | 12100.00 | $157,058.00 | |||
| $157,058.00 | ||||||
| 2017 PROPOSED ASPHALT FULL AND PARTIAL DEPTH REPAIR PROGRAM | ||||||
| ROUTE | ID | DESCRIPTION | LENGTH | WIDTH | AREA SQYD | CAPITAL FUND |
| Water break repais | 1000.00 | $60,000.00 | ||||
| Full Depth repairs | 3000.00 | $122,460.00 | ||||
| Meadowbrook Boulevard | ME-04-1579 | Hibbard to Hudson | 4225.00 | 22.00 | 1000.00 | $40,820.00 |
| Full depth subdivision repairs | 3000.00 | $122,460.00 | ||||
| $345,740.00 | ||||||
| 2017 PROPOSED CONCRETE REPLACEMENT PROGRAM | ||||||
| SUBDIVISION | DESCRIPTION | AREA SQYD | CAPITAL FUND | |||
| 30″ Combination Curb and Gutter | Eastwicke | 1000.00 | $35,000.00 | |||
| 24″ Combination Curb and Gutter | Kenwood | 750.00 | $25,500.00 | |||
| 24″ Combination Curb and Gutter | Silverwood | 700.00 | $23,800.00 | |||
| Concrete Street Replacement | Concrete Street Replacement Program | 3000.00 | $234,000.00 | |||
| $318,300.00 | ||||||
| TOTAL QUANTITIES SUM | $1,901,814.40 | |||||